Shoeing Bay PLANS
MATERIALS:
2 LENGTHS GALV PIPE 2.5” DIAMETER X 18 FOOT
4 X 2.5” GALV FLANGES
8 X 0.5” DYNABOLTS
4 X 2.5” GALV ELBOWS (IF NO PIPE BENDER AVAILABLE)
CONSTRUCTION:
AS PER DIAGRAM: Go
here for the design plans
MATERIALS:
2 LENGTHS GALV PIPE 2.5” DIAMETER X 18 FOOT
4 X 2.5” GALV FLANGES
8 X 0.5” DYNABOLTS
4 X 2.5” GALV ELBOWS (IF NO PIPE BENDER AVAILABLE)
CONSTRUCTION - AS PER DIAGRAM:
FOR ELBOWS EITHER BEND IN PIPE BENDER
OR USE READY MADE ELBOWS
ATTACH TO FLOOR EITHER WITH 2.5” GALV FLANGES DYNABOLTED
TO CONCRETE OR SET DIRECT INTO CONCRETE
RUBBER OR CONVEYOR BELT MATTING ON FLOOR HELPS SETTLE THE HORSE
AND PREVENTS SLIPPING (AVAILABLE FROM SOME DISPOSAL STORES) (ATTACH
WITH DYNABOLTS)
HORSE IS CROSS TIED USING 2 LEAD ROPES (ATTACHED TO THE RAILS
WITH BINDING TWINE FOR SAFETY) AND ALSO A LIGHT BREECHING ROPE
SHOULD BE PUT BEHIND THE HORSE’S RUMP
|